Why flexibility can change the wait

A utility sizes service for a site's maximum demand. This holds for a data center, also called a compute site. A data center's demand sits below that maximum in most hours, and the limit that holds up a connection often applies in only a few hours of the year. A site that offers to cut during those hours asks the utility to plan for less than the full maximum.

One year of hourly load with cuts in only a few hours. Illustrative.

What the Duke study found

In February 2025, researchers at Duke University's Nicholas Institute estimated how much new load the 22 largest US balancing authorities can add. Together they serve 95 percent of US peak load. Their finding was that 76 GW of new load could be integrated if the new load can be curtailed for 0.25 percent of its maximum uptime. That 76 GW equals 10 percent of the nation's current aggregate peak demand. Duke Nicholas Institute: Rethinking Load Growth

The 0.25 percent is a share of the new load's maximum annual energy use, not a share of hours. The study reports that cuts happen in about 85 hours a year on average at that rate, which is about 1 percent of the hours in a year. Most of those cuts are partial. On average, in 88 percent of those hours the new load keeps at least half of its demand. The average curtailment lasts 1.7 hours. At a 1.0 percent rate the study reports 126 GW, about 366 hours a year and an average of 2.5 hours.

The authors call the result a first-order estimate. The analysis does not account for transmission constraints. It shows system-level headroom and does not show that any single site can connect.

Three kinds of constraint

Flexibility helps differently with each one. A shortage of generation at system peaks is the problem the Duke study measures. A transmission limit and a local substation or transformer limit are different problems. A cut during the regional peak does not relieve a local transformer that peaks at another time. A credible plan names the constraint it addresses.

What a utility needs in a flexibility plan

Terms a flexibility plan defines
TermThe question it answers
Import ceilingWhat is the most the site can draw during an event?
Size of the cutHow much load comes off?
Response timeHow fast must the site be under the ceiling?
DurationHow long does the cut last?
Call authorityWho can call an event, and with how much notice?
MeteringWhich meter measures the site's draw?
RecoveryHow does the site return to normal draw afterward?

Where a site battery fits

Elastic schedules the site battery for the cut windows the utility agreement sets. The battery covers part of a cut for a limited time. The site's compute workload and cooling run under the site's own control systems. Read Where control sits on a compute site for that boundary. Read Cutting peak demand at a compute site for what limits a battery's effect. A data center can also fund flexibility in nearby homes and businesses, covered in Six ways a data center can pair power and capacity with the grid.

A 50 MW campus, for illustration

A campus plans a 50 MW draw. The utility can serve 40 MW during the constrained hours, so the site commits to cut 10 MW for each event. The site installs a battery rated 10 MW and 20 MWh and holds 4 MWh back as a reserve it does not offer for the cut. That leaves 16 MWh to cut demand.

At 10 MW, 16 MWh lasts 1.6 hours. For an event of 1.7 hours, the study's average, the battery can cover about 9.4 MW of the 10 MW cut (16 MWh divided by 1.7 hours). The remaining 0.6 MW comes from the site's own compute and cooling plans. A longer event leaves more of the cut to the site's own operations, and the utility's agreement states the terms for both.

Common questions.

Does a flexible load agreement guarantee an earlier energization date?

No. The utility decides, based on its constraint, its tariffs and the site's plan.