Where the 2026 call stands

The 2026 Call for Demand intake is closed. BC Hydro received 15 applications representing close to 800 MW in total load request, and it is reviewing them. BC Hydro extended the timeline and expects notifications after the government transition period later in 2026. BC Hydro: Emerging industries connections, read October 20, 2026.

What the call allocates, and who can apply

The province set an allocation target of up to 400 MW over the first two years. BC Government news release, January 30, 2026 BC Hydro's Request for Applications divides that into up to 100 MW for conventional data centres, and up to 300 MW plus any unused conventional capacity for AI data centres. Both are categories that the regulations define. BC Hydro can reduce either amount. BC Hydro: Request for Applications, February 1, 2026 The target, the 800 MW requested and any capacity awarded are three separate numbers.

Eligible requests run from 10 MW to 145 MW, inside BC Hydro's service area. A request can be a new facility, added capacity at an existing facility, or a change in end use. Request for Applications Projects that had signed a facilities study agreement (transmission) or paid a design deposit (distribution) by February 1, 2026 continue under the existing process. BC Hydro: Project Status Impact

Three separate numbers: up to 400 MW targeted, about 800 MW requested, the award pending.

The curtailment terms

To pass the first stage, an applicant confirms the project will curtail its electricity demand on 24 hours' notice, in any season, without incentive or compensation. The Request for Applications sets these minimums:

  • At least 10 percent of the load requested.
  • At least 4 consecutive hours in a day.
  • At least 5 days with curtailment events in each calendar week.
  • At least 2 weeks with curtailment events in each calendar month.
  • At least 36 curtailment events in each 12-month period from October 1 to September 30.
  • At least 144 hours of curtailment in each of those periods.

After the feasibility study, shortlisted applicants can amend their proposed pricing premium and their proposed curtailment in a supplemental application. Request for Applications, section 12.5 and Schedule 3 and BC Hydro: Emerging industries connections

Selection and an energized connection

Selection in the call makes a project eligible to join the interconnection queue, or lets it keep its place if it was already queued. The project then moves through BC Hydro's queue practices. BC Hydro expects supply to be governed by rate schedules, electricity supply agreements and tariff supplements, with requirements that the commitments in the application are performed and possibly performance security. Request for Applications, sections 1.1 and 15 For a selected applicant, bid security comes back 30 business days after BC Hydro starts supplying the project. It is forfeited if the applicant withdraws or leaves the queue before supply starts, or if supply has not started by December 31, 2034. Request for Applications, section 12.3

Where a site battery fits

The Request for Applications states the curtailment commitment as a reduction in the project's electricity demand. It does not mention batteries. A project that plans to run a battery during a curtailment window confirms the treatment with BC Hydro's call administrator before it relies on it.

A battery also matters for the project's own operations, inside its connection terms. Elastic schedules a site battery and reads the power flows at the site's inverter, battery and gateway meters. Each dispatch keeps a record of the command, the acknowledgement and the outcome, so a project team can see what the battery did in each window. The record is operational and does not replace utility metering. See Elastic on a compute site.